Launching gantry in both span by span and cantilever at Hong Kong (Freyssinet) for erecting Tuen Mun - Chek Lap Kok link bridge.

 

•Erection in Cantilever        120m (394ft)
•Erection in spam by span  80m   (262ft)
•Curveture                         198m  (650ft)
•Machine length                 200m  (656ft)
•Machine height                 19.4m (63.6ft)
•Longitudinal slope            6.3%
•.Transversal slope            8.4%
•Lifting  (one WT)              120tons

•Max. lifting                        2225tons
 

Special Launching Carrier with Under-bridge for passing through tunnel to erect HSR viaduct in full span method.
Lifting Capacity in 1000 tons for erecting huge box beam in full span 24-35 m.